Path closures

Next week we have a number of path closures while resurfacing work takes place. We apologise for any disruption but these works will have a positive impact on the Heath by improving path surfaces throughout.

The schedule of work is as follows:

Monday 3 October

  • Stock Pond will be closed for a short period while a tar and chip finish is added to the path.
  • Vale of Heath will be closed for a short period while a tar and chip finish is added to the path.
  • Junction of the path by Parliament Hill playground will be closed while old path is dug out.

Tuesday 4 October

  • Junction of the path by Parliament Hill playground will be closed while new tarmac is laid.
  • Causeway between Hampstead 1 and 2 will have a short closure while a tar and chip finish is added to the path.
  • Half of Mixed Pond causeway will be closed for a short period while a tar and chip finish is added to the path. The other half will remain open for pedestrian access.

Wednesday 5 October

  • Stock Pond so tarmac wagon for ladies can work from it.
  • Mixed Pond will have path repairs, but there will be pedestrian access.

Thursday 6 October

  • Other half of Mixed Pond causeway will be closed for a short period while a tar and chip finish is added to the path.
  • Path by Sports Pitch will be closed while old path is removed.

Friday 7 October

  • Path by Sports Field closed for tarmac works.

 

Advertisements
This entry was posted in Construction, Programme, Uncategorized and tagged . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s