One year in

This week marks one year of the Ponds Project, with six months left to go. The improving weather has meant good progress across the site. These pictures taken on Wednesday capture this progress.

IMG_6121

Revetment works for reed beds at Men’s Bathing Pond

IMG_6162

Placing clay at Model Boating Pond

IMG_6163

Improving and repairing paths after the Ladies Pond Building delivery

IMG_6173

Commissioning of the Ladies Pond Building

IMG_6176

The Stock Pond has now been completed apart from turfing of the spillway

IMG_6179

Grass is beginning to emerge on the downstream side of the dam face at Stock Pond

IMG_6188.JPG

Placing and compacting clay at Catchpit

IMG_6195

Oak capping now installed at Mixed Bathing Pond

IMG_6200.JPG

Excavations for inlet structure are now complete at Hampstead No. 2

IMG_6207.JPG

Preparations for a second concrete pour at Hampstead No. 1

Advertisements
This entry was posted in Construction, Programme, Uncategorized and tagged , , , , , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s