Daily Archives: February 18, 2015

A brief history of the Ponds Project – part 3 (2012 – 2015)

In December 2012,  Atkins produce  a Design Review Method Statement with input from the Ponds Project Stakeholder Group and the Hampstead Heath Consultative Committee and approval from the Hampstead Heath Management Committee. This Statement sets out the next steps of the project, … Continue reading

Posted in History | Leave a comment

A brief history of the Ponds Project – part 2 (2011 – 2012)

Continuing on from my previous post which finished in 2011, the story continues… In July 2011 the City approved an Evaluation Report setting out the broad scope of works (circa £15M) to comply with  existing and emerging reservoir legislation while … Continue reading